Work types

Top  Previous  Next

The work types register is simply a list of the different types of work executed on the project. A work code is two characters long and is used to group similar lots together and can also be used to create the default lot number when you create a new lot.

 

Adding, editing and deleting;

To edit/add information you must enable editing.
Add a new record - click on the blank row at the bottom of the list and enter the required information (work type and description).
Edit a new record - simply change it in the grid
Delete a new row - select it and press the delete button.

 

Importing and exporting

To import, open the grid context menu and select the "import work type" option and complete the Import wizard
To export, open the grid context menu and select the "export work type" option and select a save location.

 

For an overview of the more advanced features of the interface including filtering, sorting and printing - please refer to using the Grid.

 

Related Items

Work types can be linked to schedule items. This can be used to restrict the number of schedule items users must select from when adding quantities to a lot. For more information on how this works, refer to Schedule Item Links.

 

To add a schedule item, double click the Schedule Items heading in the related items panel (if it is not visible, select "show related items panel" from the context menu). A schedule item popup list will appear. Drag the schedule items(s) you want to link onto the Schedule Item heading in the related items panel.

 

The list of linked ITPs is not a direct relationship, it is inferred by an ITP and work types share link with a schedule item and as such cannot be changed.

 

clip0035

Fig 1. Work Type Register